Indicative planning
This information is indicative. EPSO reserves the right to change the information shown at any time, and regularly publishes updates.
This information is indicative. EPSO reserves the right to change the information shown at any time, and regularly publishes updates.
| Steps | Timeline |
|---|---|
| Application open | 27/07/2017 |
| Deadline for application | 26/09/2017 - 12:00(Brussels time) |
| Computer-based multiple-choice tests – testing period | 08/12/2017 - 19/12/2017 |
| Computer based multiple choice tests - results | 08/01/2018 |
| Case study – booking period | 22/02/2018 - 01/03/2018 |
| Case study | 16/03/2018 |
| Assessment Centre | 18/04/2018 - 06/06/2018 |